Enter your area and choose a project. This MOT Type 1 calculator then estimates the tonnes, bulk bags and small bags required. Many people search for it as a subbase calculator or an MOT calculator. It also compares a loose tipper delivery, counts the compaction layers and calculates the excavation depth. The second tab answers a different question: how much area will the stone you already have cover? Many builders call Type 1 hardcore or MOT1, so it works as a hardcore calculator too.

The problem

Why sub-base orders go wrong

Picture this. Three bulk bags of MOT Type 1 sit on the drive, and the patio area looks comfortably covered. Then the plate compactor passes over the first layer. The stone settles, and the finished base ends up 30 mm short.

Loose aggregate typically settles by around a tenth during compaction. Many estimates also overlook the second layer on a driveway, or the excavation that creates it. As a result, the order runs short, the spoil pile grows, and the project stops for another delivery.

Order for the finished depth: decide the compacted depth you need, then add a compaction allowance. This sub-base calculator handles both calculations before you contact the merchant.

MOT Type 1 at 100 mm
0.22 tper m²/2.2 tper 10 m²

How much MOT Type 1 per m²?

At 100 mm compacted depth, each m² requires approximately 0.22 tonnes, including 10% for compaction. A 200 mm driveway base needs double that quantity.

One 850 kg bulk bag
3.9 m²at 100 mm/7.7 m²at 50 mm

How much does a bulk bag of Type 1 cover?

A typical 850 kg bag covers approximately 3.9 m² at 100 mm. One tonne covers roughly 4.5 m² at the same compacted depth.

Quick guide

How to use the Type 1 calculator

Complete the form from top to bottom, and the tool updates every quantity together. Most estimates take about a minute.

  1. Enter the area. Add separate rectangles for L-shapes, or select a circle, a triangle or a known total area.
  2. Choose the project. The tool then suggests a typical compacted depth and the surface layers above it.
  3. Describe the ground. Soft clay or old fill generally needs a deeper base and a separating membrane.
  4. Select the material. MOT Type 1 suits nearly every project, while Type 3 and clean stone suit permeable designs.
  5. Confirm the bag sizes. Bulk bag weights vary, so check the figure on your merchant’s listing.
  6. Add prices if available. The calculator then highlights the cheapest delivery option, including or excluding VAT.

Already have some stone? Open the Coverage and tonnes tab and enter tonnes, bags or cubic metres. It then shows the area covered at your chosen depth.

The basics

What is a sub-base, and how does it differ from the base?

A sub-base, also written subbase, is the compacted layer of crushed stone under a patio, path or driveway. It spreads the load and keeps the surface level as the seasons change.

LayerWhat it isTypical depth
SurfaceSlabs, blocks, tarmac or gravel20–80 mm
Base or laying courseMortar bed, sharp sand or binder course25–60 mm
Sub-baseCompacted MOT Type 1 or similar75–250 mm
SubgradeThe natural ground, compacted after diggingNot ordered

Road engineers call the sub-base the sub-base course. For a garden patio, it simply means the Type 1 layer.

The subgrade is the soil you dig down to, while the sub-base is the stone you add. A sub-base calculator like this one works out that stone layer. In short, a strong patio foundation is a firm subgrade, a compacted sub-base and a full bed above it.

Depth guide

How deep should a sub-base be?

The correct depth depends on the expected load and the ground conditions. These compacted depths suit firm, well-drained soil, and the Type 1 calculator applies them automatically. Add 50–100 mm on soft clay, peat or made ground.

ProjectCompacted depthLayersType 1 per 10 m²
Garden path or footpath75 mm11.65 t
Patio, foot traffic100 mm12.2 t
Shed or greenhouse base100 mm12.2 t
Artificial grass75 mm11.65 t
Hot tub base150 mm23.3 t
Driveway, cars150 mm23.3 t
Driveway, vans or soft ground200 mm24.4 t
Heavy vehicles250 mm35.5 t

Tonnes include 10% for compaction. Layers assume 100 mm or less per compacted layer.

In our opinion, 100 mm under a patio and 150 mm under a car driveway are sensible minimums. A thinner base saves a bulk bag or two, but it risks sunken slabs and expensive repairs later. Our guide to why driveways sink shows what a thin base does over time.

Build-up

Patio and driveway sub-base depth and layers

The sub-base depth sets the excavation depth, so plan every layer together. These build-ups suit firm ground and match the presets in the sub-base calculator.

Patio sub-base and base layers

LayerPorcelain or stone patioConcrete slab patio
Slabs20–25 mm35–50 mm
Mortar bed40 mm40 mm
MOT Type 1 sub-base100 mm100 mm
Dig depthabout 160 mmabout 190 mm

Driveway sub-base depth

LayerBlock paving driveGravel drive
Surface60 mm blocks40–50 mm gravel
Laying course30 mm sharp sandNone
MOT Type 1 sub-base150 mm150 mm
Dig depthabout 240 mmabout 200 mm

On soft clay, add 50–100 mm of sub-base and lay a geotextile membrane first.

Gravel and tarmac drives need the same 150 mm sub-base as block paving. The surface changes, but the load on the stone underneath does not.

The formula

How to calculate how much sub-base you need

The sub-base calculator multiplies the area by the compacted depth, then by the material density. Compacted Type 1 weighs approximately 2.0 tonnes per m³, and the 10% allowance covers settlement and uneven ground.

Volume = area × compacted depth
Tonnes = volume × 2.0 × 1.10
Bulk bags = tonnes ÷ bag weight, rounded up
Example: a 5 × 3.6 m patio at 100 mm is 1.8 m³. That needs 3.96 tonnes, so five 850 kg bulk bags.

MOT Type 1 coverage per tonne and per bag

DepthCovered per tonnePer 850 kg bulk bagTonnes per m²
50 mm9.1 m²7.7 m²0.11 t
75 mm6.1 m²5.2 m²0.17 t
100 mm4.5 m²3.9 m²0.22 t
150 mm3.0 m²2.6 m²0.33 t
200 mm2.3 m²1.9 m²0.44 t
250 mm1.8 m²1.5 m²0.55 t

MOT Type 1 at 2.0 t/m³ compacted, plus 10%. Calculated with the tool on this page.

Merchant listings often quote 8–10 m² per bag at 50 mm. Our figure is slightly lower because it includes the compaction allowance. That small margin costs considerably less than a second delivery.

Buying small bags instead? One 25 kg bag covers about 0.11 m² at 100 mm, so allow nine bags per m². The Coverage and tonnes tab works as a Type 1 coverage calculator for any bag size.

How much Type 1 sub-base for common areas

AreaAt 100 mm (patio)At 150 mm (driveway)
10 m²2.2 t, 3 bulk bags3.3 t, 4 bulk bags
20 m²4.4 t, 6 bulk bags6.6 t, 8 bulk bags
30 m²6.6 t, 8 bulk bags9.9 t, 12 bulk bags
40 m²8.8 t, 11 bulk bags13.2 t, 16 bulk bags
50 m²11 t, 13 bulk bags16.5 t, 20 bulk bags

MOT Type 1 needed, with 10% for compaction, in 850 kg bulk bags. Calculated with the sub-base calculator on this page.

Example jobs

MOT Type 1 calculator examples for UK projects

We calculated each project with this MOT Type 1 calculator, using a 10% compaction allowance throughout.

Example 1: shed base

A 3 × 2.4 m shed base, 100 mm of Type 1 under a 100 mm concrete slab

Stone
7.2 m² needs 1.58 tonnes, so two bulk bags
Membrane
7.9 m² including the overlaps
Dig depth
200 mm, removing about 2.6 tonnes of soil

Two bulk bags leave a little spare for levelling. Our concrete calculator then works out the slab on top.

Example 2: porcelain patio

A 5 × 3.6 m patio, 100 mm of Type 1 under slabs on a 40 mm mortar bed

Stone
18 m² needs 3.96 tonnes, so five bulk bags
Laying
One layer, compacted with four to six plate passes
Dig depth
160 mm below the finished patio level

These figures match our patio and paving calculator exactly, which also adds the slabs and mortar.

Example 3: block paving driveway

An 8 × 5 m car driveway with 150 mm of Type 1 under block paving

Stone
40 m² needs 13.2 tonnes, laid in two 75 mm layers
Bulk bags
16 bags at £75 each come to £1,200
Loose load
14 tonnes at £35 plus £90 delivery comes to £580
Saving
The loose load saves £620, and the dig-out is 240 mm deep

The excavation produces about 17 tonnes of spoil, so book two grab lorry loads. These prices are example inputs, so replace them with your own quotes.

Example 4: artificial grass or turf

A 5 × 5 m lawn area, 75 mm of Type 1 under 25 mm of granite dust

Stone
25 m² needs 4.13 tonnes, so five bulk bags
Dig depth
100 mm before the grass goes down
Materials

Type 1, Type 3, scalpings or hardcore?

MOT Type 1 consists of crushed limestone or granite, graded from 40 mm down to dust. During compaction, the fines lock the larger stones together. That creates a strong, stable base, but one that water cannot easily pass through.

MaterialDensity usedDrains water?Best for
MOT Type 12.0 t/m³NoPaths, patios, shed bases and driveways
Type 1, recycled concrete1.9 t/m³NoThe same jobs, if certified to Clause 803
MOT Type 22.0 t/m³NoRarely stocked, so check first
MOT Type 31.8 t/m³YesPermeable driveways and SuDS
Clean gravel or 20 mm stone1.6 t/m³YesPermeable block paving bases
Ballast, 20 mm all-in1.9 t/m³PartlyLight paths only
Scalpings2.0 t/m³PartlyPaths and shed bases only
Hardcore or crusher run1.9 t/m³PartlyBulk fill below Type 1

Compacted densities used in the calculator. Check your supplier’s data sheet for its own figure.

Type 1 and Type 3 follow the Specification for Highway Works, Clauses 803 and 805. Type 3 has far fewer fines, so rain drains through, as Holcim explains. Our honest view? Choose Type 1 unless you genuinely need a permeable surface. Type 3 only performs properly with the right paving system and soil.

Can you use gravel or ballast as a sub-base? Clean gravel has no fines, so it never locks into a solid layer. Ballast compacts better, but it still falls short of Type 1 under a drive. Select any of these materials, including Type 2, Type 3 and scalpings. The type 1 sub base calculator then adjusts the tonnage automatically.

Buying it

Bulk bags or a loose tipper load?

How you buy the stone affects the price more than which merchant supplies it. Once you add your prices, the Type 1 calculator compares all three delivery options automatically.

OptionTypical sizeBest forWatch out for
Small bags20 or 25 kgRepairs under 1 tonneExpensive per tonne and slow to spread
Bulk bags800–1,000 kgPatios and shed basesA crane lorry needs firm access
Loose tipper loadFrom 4–5 tonnesDriveways and big basesIt tips where the lorry stops

Many quarries set a minimum loose load of 4–5 tonnes.

Bulk bags of MOT Type 1 cost approximately £75–£78 at national merchants in October 2026. Loose prices vary with haulage distance, so always request a delivered price per tonne. In our driveway example, the loose load cost less than half the bulk bag total.

Sub-base cost per m²

DepthBulk bags at £75Loose at £35 per tonne
100 mmabout £19 per m²about £8 per m² plus delivery
150 mmabout £29 per m²about £12 per m² plus delivery
200 mmabout £39 per m²about £15 per m² plus delivery

Stone only, using the example prices from our driveway case study. Labour and membrane are extra.

Add both prices to the Type 1 calculator, and it compares the options for your exact area and depth.

On site

How to lay and compact MOT Type 1

A durable sub-base depends on thin layers, careful compaction and patience. Follow these steps for paths, patios and driveways.

  1. Excavate to the full depth. Remove the topsoil and roots, then compact the exposed ground.
  2. Lay a geotextile membrane. It prevents the stone sinking into soft soil, so overlap every join by 300 mm.
  3. Spread the first layer. Keep each compacted layer to 100 mm or less for consistent density.
  4. Dampen and compact. Run a plate compactor across the whole layer four to six times.
  5. Repeat and check the levels. A string line and spirit level keep the falls accurate.
  6. Check the finished surface. A properly compacted base shows no footprints when you walk across it.

Planning a tarmac drive instead? Our tarmac calculator works out the asphalt tonnes for the layer above. For the full detail on depth and quality checks, read our MOT Type 1 depth and compaction guide.

Costly errors

Sub-base mistakes that cost money

Most sunken patios and rutted driveways start with one of these avoidable errors.

  1. Ordering for the loose depth. Aggregate settles during compaction, so always include an allowance.
  2. One thick layer. A plate compactor cannot consolidate 150 mm at once, so lay two thinner layers.
  3. No membrane on clay. The stone gradually pushes into the soil, and the surface dips.
  4. Forgetting the spoil. Every m² of a 240 mm dig creates over 400 kg of soil to move.
  5. Using scalpings under a driveway. They break down under car tyres and develop ruts.

Paving a front garden? Hard surfaces over 5 m² need planning permission unless water can drain through, according to GOV.UK guidance. A permeable Type 3 base can help meet that rule.

FAQ

Sub-base calculator FAQs

About 0.22 tonnes per m² at 100 mm compacted, including 10% for compaction. Use 0.33 tonnes per m² at 150 mm.

An 850 kg bag covers about 3.9 m² at 100 mm, or 7.7 m² at 50 mm.

Use 150 mm of compacted MOT Type 1 for cars. Go to 200 mm for vans or soft clay.

About 100 mm of compacted Type 1 suits most patios and shed bases. Paths can use 75 mm.

About 2.0 tonnes once compacted. Order about 2.2 tonnes per m³ to allow for settling.

Loose stone settles by roughly 10–20% under a plate compactor. The calculator adds 10% by default.

Yes on clay, soft or made ground. A geotextile membrane stops the stone sinking into the soil.

Type 1 has fines and compacts solid. Type 3 has fewer fines, so water drains through it for permeable paving.

Hardcore usually means MOT Type 1. Allow about 0.22 tonnes per m² at 100 mm, or 0.33 tonnes per m² at 150 mm.

Only under light garden paths. Ballast compacts less firmly than Type 1, so use Type 1 for patios and driveways.

Usually, once you need about 5 tonnes or more. Smaller jobs suit bulk bags.

Yes. It is free, needs no sign-up and works on phones. You can download or share every estimate as an image.

Sources and method

How the Type 1 calculator gets its numbers

The Type 1 calculator multiplies your area by the compacted depth to find the volume. It then applies the material density and your compaction allowance, before rounding up to whole bags and tonnes.

MOT Type 1 uses 2.0 t/m³ compacted, plus a default 10% allowance. Spoil uses 1.8 tonnes per m³ in the ground and expands by a quarter once excavated. These figures match our paving and aggregate calculators exactly.

Back to those three bulk bags and a base 30 mm short? Ordering for the compacted depth, plus a sensible allowance, finishes the job in one delivery. Prices checked in October 2026. Treat results as estimates, and follow your installer’s specification.

What are you building on your sub-base, and how did the ground behave when you dug? Tell us through our contact page. Real projects help us improve the calculator.